Two lines, one problem to solve
Cairo's newest growth — New Cairo, Nasr City, the New Administrative Capital, 6th of October City — happened east and west of the old city, on desert land the existing Metro never reached. The monorail is Egypt's answer: two fully automated lines built to connect that new geography back to central Cairo without adding more cars to the Ring Road.
The East Nile Line is running
The first line runs 56.5km from Stadium station in Cairo to Justice City in the New Administrative Capital, with 22 stations along the way through Nasr City and New Cairo. It was inaugurated on 20 March 2026, and full passenger service began on 6 May 2026.
The October Line is still coming
A second, 45km line with 13 stations will run from New October Station to Nile Valley Station, connecting 6th of October City and the Giza region. It's still under construction — later than its original mid-2023 target — with no confirmed opening date yet.
What both lines actually replace
Before this, commuting from New Cairo or the New Capital into central Cairo meant the Ring Road — and an hour or more in traffic was normal, not exceptional. Both monorail lines run fully automated Alstom Innovia 300 trains and connect into Cairo Metro Line 3, so a monorail trip can continue straight into the older metro network.